ACTIVITIES REPORT
Partners' Institution:
C.I.P.A.T.
Project's period (from/to):
July-September 2009
WPs concerned:
WP 5 - Test of the Training Package

Objectives of activities carried out:
- to complete revision and improvement of Module 3
- to upload Italian testing teachers' comments on experiences from other
countries
- to have a questionnaire filled by the teachers in order to write a portal
evaluation report




























Time period:
July - September 2009













Description of activities carried out:
- a number of improvements were identified following the comments on the
forum
- the 10 testing teachers commented the experiences
- the teachers filled in the questionnaire
- the questionnaire was analysed and a portal evaluation written

Outcomes:
- Module 3 was revised and a new chapter was added
- Teachers' comments were uploaded
- Portal evaluation report, based on the ten questionnaire, was submitted

Evaluation of the work undertaken:
The testing teachers showed great interest in the modules and in the experiences, though they found hard to complete all their tasks together with their usual end-of-year routine.
We were quite satisfied with their participation and cooperation.