ACTIVITIES REPORT
Partners' Institution:
Wilsthorpe Business and Enterprise College
Project's period (from/to):
October 2008 - December 2008
WPs concerned:
WP 7 - Transversal Activities

Objectives of activities carried out:
1) Dissemination of information about the project
2) Completion of Financial Reports
3) Completion of Activities Reports

Time period:
October 2008 - December 2008


Description of activities carried out:
1) Review of reasons why we have fallen behind in dissemination
activities

2) Core Team meeting to encourage support dissemination activities

3) Dissemination activities undertaken

4) Collation and submition of data for Financial Reports

5) Completion of Activities Reports

6) Forum discussions

Outcomes:
1) 12 dissemination activities carried out by 5 different members of
the Core Team, reaching at least 1500 people.

2) Financial Reports submitted and accepted.

3) Activities reports completed.

Evaluation of the work undertaken:
Progress made towards catching up on number of required dissemination activities.

Financial reports are very time consuming.